2026 City Street and Utility Project Newsletter - July 24
Published on Jul 24, 2026 16:49

This past week, the contractor completed the remaining storm sewer work. Next week, the contractor will place the remaining curb and gutter and get the roads ready for paving. The first layer of pavement is currently scheduled to be placed on Tuesday, Aug. 4. There will be minor delays during paving operations, but vehicles will have access soon after the paver passes your house.
Please note: You may notice vibration during the compaction process. Once the first layer of pavement is placed, the contractor will replace bituminous driveways and then restore yards.
If you have any questions, feel free to contact Lucas Gross at (612) 791-8423 or via email at [email protected].
Thank you for your patience as the city works to improve the infrastructure in your neighborhood.
|