|
2025 City Street and Utility Project Newsletter - Nov. 6
Published on Nov 6, 2025 18:01

Proposed 2-Week Construction Schedule
(Idaho Ave.)
Nov. 10 – Nov. 14
- Temporary
paving wedge along curb lines for winter plowing.
- Tress
to be planted.
(Jersey Ave.)
Nov. 10 – Nov. 14
- Temporary paving wedge
along curb lines for winter plowing.
- Tree to be planted.
Traffic Impacts and Parking|
During the construction period, there will be no on-street parking on the following streets between 7 a.m. to 6 p.m.
• Jersey Ave. N. between 29th Ave. N. and Medicine Lake Road.
• Idaho Ave. between 31st Ave. N. and 30th Ave. N.
Weather Considerations
Remember that the project is weather-dependent, and activities may be delayed if adverse conditions arise. We will keep you informed of any schedule changes as they occur.
Contact Information
If you have any questions or concerns about the construction project, contact Bruce Brown at 651-418-7619 or [email protected].
We appreciate your patience and cooperation as we work to improve the streets and utilities in your neighborhood. We will continue to keep you updated on the progress of the project.
|