2025 City Street and Utility Project Newsletter Sept. 25
Published on Sep 25, 2025 10:31

Proposed 2-Week Construction Schedule
(Idaho Ave.)
Sept. 2 – Oct. 3
• Start hauling topsoil middle of this week.
• Irrigation and dog fence repairs.
• Sodding end of the week.
Sept 6 – Oct. 10
• Sodding continues into this week.
(Jersey Ave.)
Sept. 29 – Oct. 3
• Roadway work continues by excavating and installing fabric, sand and gravel.
• Storm sewer installation will finish up as the roadway work continues through.
• Curb and Gutter scheduled for Wednesday Oct. 1.
• Concrete Driveways scheduled for installation on Thursday Oct. 2.
Sep. 6 – Oct. 10
• Start grading gravel for paving
• Backfill curbs and gutters.
Traffic Impacts and Parking
During the construction period, there will be no on-street parking on the following streets between 7 a.m. to 7 p.m.
• Idaho Ave. N. between 30th Ave. N. and 31st Ave.
• Jersey Ave. N. between 30th Ave. N. and Medicine Lake Rd.
• Curb and Gutter parking notices will be handed out early next week with more information on parking and times of how long you will need to stay off the concrete curb and driveways.
Weather Considerations
Please remember that the project is weather-dependent, and activities may be delayed if adverse conditions arise. We will keep you informed of any schedule changes as they occur.
Irrigation and Dog Fences
Please help the contractor by marking dog fences and irrigation. Repairs will be taking place on Idaho this week and on Jersey in the coming weeks.
Contact Information
If you have any questions or concerns about the construction project, do not hesitate to contact Bruce Brown at 651-418-7619 or [email protected].
We appreciate your patience and cooperation as we work to improve the streets and utilities in your neighborhood. We will continue to keep you updated on the progress of the project.
|