Proposed Two-week Construction Schedule
(Idaho Ave.) Sept. 8 – 12
• Grading aggregate base for first lift of asphalt pavement.
• Paving first lift of asphalt paving Wednesday or Thursday this week.
Sept. 15 – 19
• Restoration next week of yards.
• Asphalt driveways to be installed early in the week.
(Jersey Ave.) Sept. 8 – 12
• Watermain work continues from 30th to the south.
• Watermain services being installed from 29th to Medicine.
Sept. 15 – 19
• Watermain services from 29th to 30th.
• Storm sewer work to begin next week.
Traffic Impacts and Parking
During the construction period, there will be no on-street parking on the following streets between 7 a.m. to 7 p.m.
• Idaho Ave. N. between 30th Ave. N. and 31st Ave.
• Jersey Ave. N. between 30th Ave. N. and Medicine Lake Rd.
Idaho residents can access their driveways starting Thursday Sept. 11 after base lift of paving is completed.
Weather Considerations
Please remember that the project is weather-dependent, and activities may be delayed if adverse conditions arise. We will keep you informed of any schedule changes as they occur.
Contact Information
If you have any questions or concerns about the construction project, please do not hesitate to contact:
• Bruce Brown at 651-418-7619 or [email protected].