 The city is making important improvements to your neighborhood’s streets and utilities. Please see the two-week construction schedule below for details about what to expect.

Idaho Ave. Construction Schedule

Aug. 18–22

  • Installation of new water and sanitary services to homes early in the week.
  • Street reconstruction begins: excavation, fabric, sand, and gravel work in preparation for curb installation.

Aug. 25–29

  • Street reconstruction wraps up early in the week.
  • Curb and gutter installation begins.
  • Concrete driveway installation may also begin.

Jersey Ave. Construction Schedule

Aug. 18–22

  • Asphalt removal (reclaiming/grinding).
  • Driveways will be removed and temporarily replaced with gravel.
  • Temporary water connections will be installed using hoses attached to your outside spigots (this is to maintain water service during watermain construction).

Aug. 25–29

  • Utility construction is scheduled to begin.

Traffic and Parking Notice
There will be no on-street parking between 7 a.m. – 7 p.m. on the following streets during construction:

  • Idaho Ave. N. (from 30th Ave. N. to 31st Ave. N.)
  • Jersey Ave. N. (from 30th Ave. N. to Medicine Lake Rd.)

Weather Reminders
Please note: Construction activities may be delayed due to weather. The city will notify you of any schedule changes as they happen.

Have Questions?
Contact:
Bruce Brown
651-418-7619
[email protected]

Thank you for your continued patience and cooperation as we improve the infrastructure in your neighborhood. We’ll keep you updated as work progresses.

Go To Homepage
City of Crystal